Emergency work at the Qods Amendis substation for Veolia Morocco

02.04.2014

Following a fire at the Qods Amendis source substation which led to total black-out in the town of Tétouan for over 2 hours, Clemessy Morocco was asked to take emergency action and set up a temporary 60/20 kV transformer facility.

In order to do so, Clemessy Morocco handled the following:

  • Loading, transporting and unloading an existing 20MVA transformer from the « Chef Laakab » substation in Amendis Tangiers to the Qods substation in Tétouan
  • Supplying all the HV/MV/LV equipment necessary to upgrade the transformer span
  • The erection and connection works for this transformer span
  • The electrical and functional tests
  • Putting the 20 MVA transformer into service

Clemessy Morocco team who replaced the Qods Amendis source substation